Final case: three communication paths

Time: about 7–10 minutes including the task; estimate

Guiding question: Can you explain three communication paths and their failure cases?

Learning objective: You explain three complete communication paths and assign failures correctly.

Prerequisites: Previous lessons through 2.21, particularly the case file developed there.

Three paths, one shared understanding

Talbahn is preparing an integration trial. Lea drives FRMCS train 1234; Niko works at the dispatcher terminal. For the mixed voice case, Amir explicitly drives GSM-R train 5678. The separate FRMCS test device from the MCPTT example is not his vehicle equipment in this trial. A diagnostic application also transfers vehicle data. All details belong to a fictional teaching case.

This task connects the previously explained functions. Each path needs an origin, counterpart, application integration, service, transport and success criterion. An architecture diagram alone is insufficient: explain how communication is prepared, established, used and terminated.

Your task

Create three annotated paths: an FRMCS voice call between Lea and Niko, a data case between on-board and trackside applications, and a mixed call with Amir through the IWF. Mark control and user data for each. Then describe a failure: missing service authorisation, rejection by the remote application, or IWF failure. Assign each failure to its appropriate path.

Model solution

For voice, network and service access are prepared. The selected voice application uses its MCPTT client functions. SIP-based control supports establishment; service-specific functions determine participation and floor. Media must reach the correct audio output. Successful radio access does not repair missing service authorisation.

For data, we use the loosely coupled H2H variant. The on-board application requests its session. MCData and trackside integration connect the intended partners. Rejection by the remote application is different from packet loss after successful establishment. Application boundary, gateway and service receive separate observations.

For the mixed call, only the IWF's demonstrated functionality is assumed. Identities, call behaviour, floor control, media and priority need suitable mappings. IWF failure may interrupt the cross-system path while internal FRMCS communication still works. An alternative procedure is proposed only if equipment, permission and an approved procedure exist.

“FRMCS installed” is insufficient for every path. Talbahn needs a combination of application profile, implementation and observable result. [S07; S09; S11; S42]

Self-assessment

Score six criteria with 0 for missing/incorrect, 1 for partial and 2 for explained: correct partners; application integration; service states; control/user-data separation; failure assignment; appropriate evidence. The maximum is 12 points. At least 10 is a useful threshold for level 3. Regardless of score, keep service and transport separate and do not present the IWF as a universal function converter.

What to remember

You can now follow communication through the architecture and assign observations to the correct functions. Level 3 uses this understanding for project decisions.

Your Talbahn case file

Retain the three paths as references. Record open technical questions explicitly rather than replacing them with assumed product capabilities.

Sources

  • S07 · ETSI TS 103 764: FRMCS System Architecture

    ETSI TS 103 764: FRMCS System Architecture

    Version: 1.1.1, January 2026 · Checked: 2026-10-11

    Scope: Architecture sections: FRMCS boundary, service and transport, applications using the system.

    Limitations: Course diagrams are original simplifications, not normative reference drawings.

    Used in: 1.3, 1.5, 1.8, 1.9, 1.10, 2.1, 2.22

  • S09 · ETSI TS 103 765-2: FRMCS Service Stratum

    ETSI TS 103 765-2: FRMCS Service Stratum

    Version: 1.1.1, January 2026 · Checked: 2026-10-11

    Scope: Service architecture; SIP Core definition; registration and MC services.

    Limitations: Do not equate IMS with SIP; the architecture allows the specified SIP Core alternatives.

    Used in: 1.9, 2.1, 2.4, 2.5, 2.6, 2.7, 2.8, 2.9, 2.10, 2.14, 2.19, 2.22, 3.5, 3.16

  • S11 · ETSI TS 103 792: FRMCS/GSM-R Interworking

    ETSI TS 103 792: FRMCS/GSM-R Interworking

    Version: 1.1.1, January 2026 · Checked: 2026-10-11

    Scope: Interworking architecture and defined functional mediation.

    Limitations: Demonstrate support per function and combination; not universal ETCS translation.

    Used in: 1.10, 2.7, 2.20, 2.22

  • S42 · ETSI TS 103 765-4: Trackside functions and interfaces

    ETSI TS 103 765-4: Trackside functions and interfaces

    Version: 1.1.1 (2026-01) · Checked: 2026-10-11

    Scope: Clauses 4–6: Trackside Gateway, context and procedures.

    Limitations: Named teaching edition; no blanket product or project approval.

    Used in: 2.1, 2.9, 2.12, 2.22, 3.3, 3.5

Shared source register

Your progress is stored in this browser on this device.

End of this levelLevel overviewContinue with level 3: Design →